Who is responsible for reviewing and approving or denying change requests?

  1. Project manager

  2. Change control board

  3. Project team members

  4. Stakeholders

The correct answer is: Change control board

The correct answer is the Change Control Board (CCB). The CCB is responsible for reviewing and approving or denying change requests in a project. The CCB consists of relevant stakeholders who assess the impact of the proposed changes on the project scope, schedule, budget, and overall objectives. They ensure that changes are thoroughly evaluated before being implemented to prevent unnecessary disruptions to the project. Project managers, project team members, and stakeholders may be involved in the change request process, providing input and insights; however, the ultimate responsibility for reviewing and approving or denying change requests lies with the Change Control Board.