CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which tools and techniques are used in the estimate activity durations process?

  1. Expert judgment and analogous estimating only

  2. Parametric estimating and project management software

  3. Analogous estimating, three-point estimating, and reserve analysis

  4. Resource leveling and critical path method

The correct answer is: Analogous estimating, three-point estimating, and reserve analysis

Analogous estimating, three-point estimating, and reserve analysis are all used in the estimate activity durations process. Expert judgment and analogous estimating are incorrect because while they may be used in other processes, they are not specifically mentioned in the estimate activity durations process. Parametric estimating and project management software may also be used in other processes, but they are not mentioned as tools specifically used in the estimate activity durations process. Resource leveling and critical path method are also not correct because while they may be used in other processes, they are not listed as tools and techniques used in the estimate activity durations process.