Which technique is used in plan communication management?

  1. Communication requirements analysis

  2. Budget estimation

  3. Risk management

  4. Resource leveling

The correct answer is: Communication requirements analysis

Communication requirements analysis is the technique used in plan communication management. This involves identifying the information needs of the project stakeholders, determining who needs what information, and when they will need it. By analyzing the communication requirements, the project manager can develop an effective communication plan to ensure that the right information is delivered to the right stakeholders at the right time. Budget estimation, risk management, and resource leveling are important aspects of project management, but they are not specifically related to the technique used in plan communication management.