Which scheduling methods are activity network diagrams used with?

  1. AOA and AON

  2. WBS and OBS

  3. PERT and SWOT

  4. CPM and PDM

The correct answer is: CPM and PDM

Activity Network Diagrams are used with the Critical Path Method (CPM) and the Program Evaluation and Review Technique (PERT). These methods help project managers to visualize and analyze the sequence of activities, dependencies, and the critical path in a project schedule. AOA (Activity on Arrow) and AON (Activity on Node) are specific types of representations within CPM. Therefore, the correct answer is D, as Activity Network Diagrams are commonly associated with CPM and PERT.