Which of the following is a tool or technique used in the develop project team process?

  1. Work performance reports

  2. Team-building activities

  3. Stakeholder engagement plan

  4. Change request forms

The correct answer is: Team-building activities

Team-building activities are considered a tool or technique used in the develop project team process. Team-building activities are essential to promote trust, improve communication, enhance collaboration, and strengthen relationships within the project team. By engaging in team-building activities, project team members can bond, understand each other's working styles, and ultimately work more effectively together to achieve project goals. On the other hand, the other options may not directly relate to the develop project team process: A. Work performance reports are part of the monitoring and controlling process group, used to track and report on the project's performance. C. Stakeholder engagement plan is a tool used in the plan stakeholder engagement process to outline strategies for effectively engaging stakeholders throughout the project. D. Change request forms are typically used in the perform integrated change control process to document and manage changes to the project.