CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which of the following is not one of the 3 baseline plans?

  1. Scope baseline plan

  2. Schedule baseline plan

  3. Cost baseline plan

  4. Quality baseline plan

The correct answer is: Quality baseline plan

The correct answer is D, Quality baseline plan. In project management, the three baseline plans are the Scope baseline plan, Schedule baseline plan, and Cost baseline plan. These three baselines are essential for monitoring and controlling the project throughout its lifecycle. The Quality baseline plan is not one of the main baseline plans in project management, although quality management is crucial for project success.