Which of the following is a deliverable of the implementation and execution phase?

  1. Risk Assessment

  2. Procurement of Goods and Services

  3. Feasibility Studies

  4. Reassignment or Release of Resources

The correct answer is: Procurement of Goods and Services

During the implementation and execution phase of a project, one of the key deliverables is the procurement of goods and services. This involves acquiring the necessary resources, materials, and services needed to carry out the project activities as planned. The procurement process ensures that the project team has the right resources available to complete the project successfully. Therefore, B is the correct answer. On the other hand: A. Risk Assessment is typically conducted during the project planning phase to identify and evaluate potential risks. C. Feasibility Studies are usually conducted in the project initiation phase to assess the feasibility of the project. D. Reassignment or Release of Resources may occur during various phases of the project but is not specifically a deliverable of the implementation and execution phase.