CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which of the following is a typical output of the determine budget process?

  1. Resource calendars

  2. Project funding requirements

  3. Stakeholder engagement plan

  4. Communications breakdown structure

The correct answer is: Project funding requirements

The correct answer is B. Project funding requirements. During the Determine Budget process, one of the key outputs is to establish the cost baseline for the project, including the funding needed to execute the project successfully. This output outlines the financial resources required for the project activities, enabling the project manager to allocate funds appropriately and manage the project within the approved budget. Option A, Resource calendars, is typically an output of the Develop Schedule process, not the Determine Budget process. Option C, Stakeholder engagement plan, is an output of the Plan Stakeholder Engagement process. Option D, Communications breakdown structure, is not a standard output of any Project Management process.