Which of the following is NOT an input of plan communication management?

  1. Project management plan

  2. Stakeholder register

  3. Communication requirements analysis

  4. Enterprise environmental factors

The correct answer is: Communication requirements analysis

Communication requirements analysis is not an input of plan communication management because it is a tool and technique used in the Plan Communications Management process, rather than an input into it. The communication requirements analysis helps in determining the communication needs of stakeholders and identifying what information needs to be communicated, in what format, and through which channels. The other options listed are inputs of plan communication management: A. Project management plan: This is a key input as it provides the overall direction and guidance on how communication activities will be planned, executed, monitored, and controlled throughout the project. B. Stakeholder register: This input helps in identifying the stakeholders who are involved in or impacted by the project, along with their communication needs and expectations. D. Enterprise environmental factors: These factors include the organizational culture, structure, and communication infrastructure, which can influence how communication is planned and executed within the project.