Which of the following is an input to the control schedule process?

  1. Project calendars

  2. Financial documents

  3. Legal contracts

  4. Vendor quotations

The correct answer is: Project calendars

The project calendar, which is created and updated as part of the project management plan, is a key input to the control schedule process. It provides information about when and how long resources are available, which is essential for controlling the project schedule. Financial documents, legal contracts, and vendor quotations are all important inputs to other project processes, but they are not specifically related to controlling the schedule.