CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which of the following is NOT listed under the outputs of control stakeholder engagement?

  1. Org process assets updates

  2. Work breakdown structure updates

  3. Project management plan updates

  4. Project docs updates

The correct answer is: Work breakdown structure updates

Control Stakeholder Engagement is the process of monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders. The outputs of this process include updates to organizational process assets, project management plan, and project documents. However, updates to the work breakdown structure (WBS) are not typically listed under the outputs of control stakeholder engagement. The correct answer is B because the WBS is a project management tool used for defining the total scope of the project, not specifically related to stakeholder engagement activities.