Which of the following is NOT a process of Project Time Management?

  1. Estimate Activity Resources

  2. Control Schedule

  3. Perform Quality Assurance

  4. Define Activities

The correct answer is: Perform Quality Assurance

Perform Quality Assurance is not a process of Project Time Management because it is a process within Project Quality Management. Project Time Management includes processes such as Define Activities, Estimate Activity Resources, and Control Schedule, which focus on defining, estimating, and controlling the project's schedule activities. Quality Assurance processes, on the other hand, are focused on ensuring that the project delivers the required quality standards and is not directly related to managing the project's schedule activities.