Which of the following are types of scheduling charts?

  1. Milestone chart, network diagram, time-scaled network diagram, Gantt chart

  2. Pie chart, bar graph, scatter plot, histogram

  3. Flow chart, organizational chart, PERT chart

  4. SWOT analysis chart, risk matrix, cost-benefit analysis chart

The correct answer is: Milestone chart, network diagram, time-scaled network diagram, Gantt chart

Options B, C, and D are incorrect because they are not types of scheduling charts. A pie chart, bar graph, scatter plot, and histogram are used to represent data, while a flow chart, organizational chart, and SWOT analysis chart are used to visualize processes or relationships. A PERT chart and risk matrix are similar to scheduling charts, but do not display a timeline. Therefore, A is the correct answer as it lists different types of scheduling charts that are specifically used for planning and managing projects.