CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which is not listed as a tool or technique of plan procurement management?

  1. Expert judgment

  2. Procurement documents

  3. Market research

  4. Meetings

The correct answer is: Procurement documents

Expert judgment is a valuable tool in plan procurement management as it draws on the expertise and industry knowledge of experienced professionals. Market research is also essential as it allows for a thorough understanding of the current market conditions and helps to identify potential suppliers. Meetings are necessary for effective communication between all parties involved in the procurement process. Procurement documents, while important for the procurement process, are not considered a tool or technique as they are simply documentation that outlines the procurement activities and requirements. Therefore, option B is incorrect as it is not a tool or technique listed in plan procurement management.