Which enterprise environmental factor can influence plan procurement management?

  1. Marketplace conditions

  2. Project schedule

  3. Activity cost estimates

  4. Risk register

The correct answer is: Marketplace conditions

Enterprise environmental factors (EEFs) refer to conditions not under the control of the project team that can have an impact on the project. In the context of plan procurement management, marketplace conditions are an important EEF to consider. This includes factors such as current market trends, availability of suppliers, and pricing conditions. It is important for the project team to be aware of these factors in order to develop a realistic and effective procurement plan. The other options may be relevant to other areas of project management, but they do not directly influence plan procurement management. Project schedule and activity cost estimates are specific to the project itself, while the risk register is a tool used for risk management and not procurement management. Therefore, A is the correct answer as it is the only option that directly relates to the question.