CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which are tools and techniques of create WBS process?

  1. Inspection and audits

  2. Decomposition and expert judgment

  3. Risk analysis

  4. Cost benefit analysis

The correct answer is: Decomposition and expert judgment

The create WBS process involves breaking down project deliverables and work into smaller, more manageable components. This is known as decomposition. Expert judgment is also used in this process to ensure that the WBS is accurate and comprehensive. Inspection and audits are not directly related to creating a WBS, although they may be used later on to ensure the accuracy of the WBS. Risk analysis typically occurs during the planning phase and is not a tool used specifically in creating a WBS. Cost benefit analysis is used to evaluate the value of a project, but is not a tool used in the create WBS process. Therefore, the correct answer is B Decomposition and expert judgment.