CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What phase comes last in the project life cycle?

  1. Concept phase

  2. Development/Planning phase

  3. Implementation/Execution phase

  4. Termination/Close phase

The correct answer is: Termination/Close phase

The Termination/Close phase is the final phase in the project life cycle. During this phase, all project work is completed and the project is formally closed. This includes reviewing project performance, documenting lessons learned, and transitioning final deliverables to the stakeholders. The other options are incorrect because the Concept phase is the first phase, the Development/Planning phase comes before the Implementation/Execution phase, and both of these phases occur before the final phase of Termination/Close.