What is the purpose of the plan scope management process?

  1. To outline the project's budget

  2. To document how scope will be defined, validated, and controlled

  3. To assign project tasks to team members

  4. To finalize the project's deliverables

The correct answer is: To document how scope will be defined, validated, and controlled

The purpose of plan scope management process is to document the strategy for how project scope will be defined, validated, and controlled. It is not related to outlining the project's budget (Option A), assigning project tasks to team members (Option C), or finalizing the project's deliverables (Option D). It is solely focused on managing the scope of the project.