What is the output of plan HR management?

  1. Financial management plan

  2. Human resource management plan

  3. Quality management plan

  4. Risk management plan

The correct answer is: Human resource management plan

The output of planning HR management is a human resource management plan. This plan includes processes for identifying, acquiring, developing, and managing project team members. Options A, C, and D are incorrect because they do not directly pertain to human resources and may be separate plans within a project management plan. For example, the financial management plan would focus on project budgeting and cost control, while the quality management plan would focus on ensuring project deliverables meet specified quality standards. The risk management plan would outline processes for identifying, analyzing, and responding to potential risks on the project. While these plans may have some overlap with HR management, they do not address the specific processes and considerations involved in managing project team members. Therefore, they are not the correct output of planning HR management.