What is the main use of Gantt charts?

  1. To measure the progress of a project

  2. To compare future data to past data

  3. For financial budgeting

  4. To identify stakeholders

The correct answer is: To measure the progress of a project

Gantt charts are primarily used for project management as they provide a visual representation of the project timeline and tasks. Option A is the best choice because it directly relates to project management while the other options do not. While Gantt charts may be able to provide some insight for financial budgeting or identifying stakeholders, these are not the main uses for Gantt charts. Option B also mentions comparing data, but Gantt charts are not typically used for comparing past and future data, rather they focus on tracking progress and timelines. Overall, option A is the best answer as it clearly identifies the main use of Gantt charts.