CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is the main goal of the estimate activity durations process?

  1. To finalize the project's budget

  2. To define the project's scope

  3. To estimate the number of work periods needed to complete activities with estimated resources

  4. To assign specific tasks to team members

The correct answer is: To estimate the number of work periods needed to complete activities with estimated resources

The main goal of the estimate activity durations process is to estimate the number of work periods needed to complete activities with estimated resources. This process focuses on determining the time it will take to complete each specific activity within the project. By accurately estimating the duration of each activity, project managers can schedule tasks efficiently, allocate resources effectively, and ultimately, manage the project timeline to ensure timely completion. Options A, B, and D are not correct because: A. The finalize project's budget typically involves cost estimation processes, whereas estimating activity durations focuses on time rather than budget. B. Defining the project's scope is part of the project initiation phase and is separate from estimating activity durations. D. Assigning specific tasks to team members is part of the resource assignments process and is not the primary goal of estimating activity durations.