What is the focus of the executing process in project management?

  1. To close each project phase and obtain approval

  2. To integrate all resources to carry out the project plan

  3. To audit the project's compliance with industry standards

  4. To reassess the project's objectives and deliverables

The correct answer is: To integrate all resources to carry out the project plan

The focus of the executing process in project management is to integrate all resources to carry out the project plan. During the executing process, the project team works together to complete the work defined in the project management plan and deliver the project's objectives. This phase involves coordinating people and resources, as well as managing stakeholder expectations to ensure the successful execution of the project plan. Hence, option B is the correct answer. Options A, C, and D are not the focus of the executing process: A. Closing each project phase and obtaining approval is part of the process group known as Closing, not Executing. C. Auditing the project's compliance with industry standards typically occurs during quality assurance activities in the project, not specifically during the executing process. D. Reassessing the project's objectives and deliverables might happen during monitoring and controlling phases to ensure alignment with the project plan, but it is not the primary focus of the executing process.