CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is primarily concerned with in Project Cost Management?

  1. Managing Teams

  2. Controlling Risks

  3. Managing Costs

  4. Ensuring Timely Completion

The correct answer is: Managing Costs

Project Cost Management is primarily concerned with managing the costs associated with the project. This includes budgeting, estimating, and controlling costs throughout the project lifecycle. Option A, managing teams, is a responsibility of Human Resource Management. Option B, controlling risks, is a responsibility of Risk Management. Option D, ensuring timely completion, is a responsibility of Schedule Management. However, these areas may interact and affect project cost management.