CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is ETC an acronym for?

  1. Estimated time to complete

  2. Estimate to complete

  3. Early termination cost

  4. Estimated total cost

The correct answer is: Estimate to complete

ETC stands for Estimate to Complete. This term represents the projected cost to finish all the remaining work for a particular project activity or the project as a whole. It is an essential aspect of project management as it helps in assessing the overall project budget and progress.