What is emphasized in project quality?

  1. Ensuring that the project's constraints are addressed

  2. Developing a new product

  3. The number of team members

  4. Implementing the best technology

The correct answer is: Ensuring that the project's constraints are addressed

In project quality, the emphasis is on ensuring that the project's constraints are addressed. This includes meeting the requirements and expectations set for the project in terms of scope, time, cost, and quality. By addressing the project's constraints effectively, project quality is maintained, and the project is executed successfully. The other options are not directly related to what is typically emphasized in project quality. Developing a new product, the number of team members, and implementing the best technology are important aspects of project management but do not directly relate to the primary focus of project quality, which is ensuring that the project's constraints are met.