CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is defined in the WBS dictionary as part of the basis of estimate?

  1. Project scope statement

  2. Rationale for estimates

  3. Resource breakdown structure

  4. Project schedule

The correct answer is: Rationale for estimates

The correct answer is B. Rationale for estimates is defined in the Work Breakdown Structure (WBS) dictionary as part of the basis of estimate. Option A, project scope statement, is a key document that outlines the deliverables and boundaries of the project but is not specifically related to the basis of estimate. Option C, resource breakdown structure, is a hierarchical representation of resources by category and type which is not directly related to the basis of estimate. Option D, project schedule, is a detailed timetable that includes start and end dates of project activities but again is not identified as part of the basis of estimate. Therefore, the best choice is B as it specifically relates to the rationale behind the estimates provided in the WBS dictionary.