What is an output of the estimate activity durations process?

  1. Project budget adjustments

  2. Activity duration estimates

  3. Final project deliverables

  4. Complete project timeline

The correct answer is: Activity duration estimates

The output of the estimate activity durations process is activity duration estimates. During this process, the project team estimates the duration of each activity based on resource availability, historical data, and other factors. These estimates are crucial for developing an accurate project schedule. Options A, C, and D are incorrect because project budget adjustments, final project deliverables, and a complete project timeline are not direct outputs of the estimate activity durations process. While these elements may be influenced by the activity duration estimates, they are not the specific output of this particular process.