What is an output of the control schedule process?

  1. Stakeholder satisfaction surveys

  2. Quality metrics

  3. Schedule forecasts

  4. Budget estimates

The correct answer is: Schedule forecasts

The correct answer is C. Schedule forecasts. During the control schedule process, one of the key outputs is generating schedule forecasts. Schedule forecasts help project managers anticipate future project schedule performance based on past performance and current conditions. This output is crucial for making informed decisions to keep the project on track and to identify any potential schedule deviations early on. Choices A, B, and D are incorrect as they are not direct outputs of the control schedule process. Stakeholder satisfaction surveys are more related to stakeholder management processes, quality metrics are associated with the control quality process, and budget estimates are typically part of the cost management processes.