What is an example of an output from the sequence activities process?

  1. Resource breakdown structure

  2. Project schedule network diagrams

  3. Risk register

  4. Cost management plan

The correct answer is: Project schedule network diagrams

One example of an output from the sequence activities process is a project schedule network diagram. This diagram shows the logical relationships between all the project activities, their sequence, and the dependency among them. This output is important as it helps in building the project schedule. The other options are incorrect because A: Resource breakdown structure is an output of the define activities process and it shows the resources needed for each project activity. C: Risk register is an output of the identify risks process and it contains all the identified project risks. D: Cost management plan is an output of the plan cost management process and it outlines how the project costs will be planned, structured and controlled.