What is a contingency plan?

  1. A detailed step-by-step plan for the entire project

  2. A response to a risk that might happen

  3. A backup plan if the project fails

  4. A response to a risk event that will be implemented only if the risk event occurs

The correct answer is: A response to a risk event that will be implemented only if the risk event occurs

A contingency plan is a specific response prepared to address a risk event if it materializes during the project. It is not a detailed step-by-step plan for the entire project (choice A), as it is focused on managing specific risks. Additionally, while a contingency plan can help manage project risks, it is not an overall backup plan in case the entire project fails (choice C). The correct answer, option D, accurately describes a contingency plan as a response that will be implemented only if the risk event actually occurs, making it an important component of risk management within a project.