What does three-point estimating involve?

  1. Calculating an average of four different estimates

  2. Taking the average of three estimated durations - optimistic, most likely, pessimistic

  3. Estimating the start, middle, and end points of a project

  4. Using past project data to predict future timelines

The correct answer is: Taking the average of three estimated durations - optimistic, most likely, pessimistic

Three-point estimating involves taking the average of three estimated durations: optimistic, most likely, and pessimistic. This technique helps in providing a more accurate and realistic estimate by considering different scenarios rather than relying solely on one estimation. Option A is incorrect because it mentions calculating an average of four different estimates, which is not how three-point estimating is typically done. Option C is incorrect as it describes estimating the start, middle, and end points of a project, which is not specific to three-point estimating. Option D is incorrect as it refers to using past project data to predict future timelines, which is a different concept from three-point estimating.