CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What does the staffing management plan include?

  1. Only staff acquisition plan and resource calendar

  2. Training needs and budget allocation

  3. Staff acquisition plan, resource calendar, staff release plan, training needs, recognitions and rewards, compliance with roles, safety policies and procedures

  4. Project timelines and deadline schedules

The correct answer is: Staff acquisition plan, resource calendar, staff release plan, training needs, recognitions and rewards, compliance with roles, safety policies and procedures

The staffing management plan includes a comprehensive set of elements to ensure effective project resource management. This includes the staff acquisition plan, resource calendar, staff release plan, training needs, recognitions and rewards, as well as compliance with roles and safety policies and procedures. These components are essential for managing human resources throughout the project's lifecycle, ensuring that the right people are in the right roles with the necessary support and training to successfully execute the project. Options A and D do not fully capture the breadth of elements included in the staffing management plan. Option B focuses solely on training needs and budget allocation, missing other crucial aspects of the plan. Therefore, option C is the correct choice as it provides a comprehensive overview of what the staffing management plan encompasses in project management.