CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What does the requirements management plan describe?

  1. How the project's expenses will be managed

  2. How requirements will be analyzed, documented, and managed

  3. The project's communication plan

  4. The project's risk management strategies

The correct answer is: How requirements will be analyzed, documented, and managed

The requirements management plan describes how requirements will be analyzed, documented, and managed throughout the project. This plan outlines the process for gathering, documenting, prioritizing, and maintaining project requirements. It ensures that all project stakeholders have a clear understanding of what needs to be delivered and helps prevent scope creep by managing changes to requirements effectively. Option A is incorrect because it refers to cost management, which is not the primary focus of the requirements management plan. Option C is incorrect as the communication plan is a separate document that outlines how project communication will be managed. Option D is incorrect as risk management strategies are detailed in the risk management plan, not the requirements management plan.