What does the activity attributes identify?

  1. Different project phases

  2. Multiple components of each activity

  3. Only the project calendar

  4. Just the person responsible for the activity

The correct answer is: Multiple components of each activity

Activity attributes are a set of multiple components associated with each activity in a project. These components may include activity codes, constraints, assumptions, resource requirements, predecessor activities, successor activities, and much more. By identifying and documenting these attributes, project managers can effectively plan, execute, and monitor each activity within the project. Therefore, option B is the correct answer.