What does performance reviews involve?

  1. Negotiating with suppliers

  2. Measuring, comparing, and analyzing performance in relation to the schedule

  3. Conducting surveys on team morale

  4. Evaluating project risks

The correct answer is: Measuring, comparing, and analyzing performance in relation to the schedule

Performance reviews involve measuring, comparing, and analyzing performance in relation to the schedule. This process helps project managers and team members assess how well the project is progressing in terms of timelines and milestones. It allows them to identify any deviations from the schedule and take corrective actions if necessary. This data is crucial for making informed decisions and ensuring the project stays on track. The other options - negotiating with suppliers, conducting surveys on team morale, and evaluating project risks - are important in project management but are not directly related to the definition of performance reviews.