CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What does a positive Schedule Variance (SV) indicate?

  1. The project is exactly on schedule

  2. The project is behind schedule

  3. The project is over budget

  4. The project is ahead of schedule

The correct answer is: The project is ahead of schedule

A positive Schedule Variance (SV) indicates that the project is ahead of schedule. This means that the planned progress and work completed are ahead of the scheduled timeline. Option A is incorrect because being exactly on schedule would have an SV of 0. Option B is incorrect because a negative SV indicates that the project is behind schedule. Option C is incorrect because a positive SV indicates schedule progress, not budget performance. Therefore, option D is the correct answer.