CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What describes a start-to-start logical relationship?

  1. The successor's finish is dependent on the predecessor's start

  2. The successor and predecessor start at the same time

  3. The successor cannot start until the predecessor starts

  4. The successor's start is independent of the predecessor's start

The correct answer is: The successor cannot start until the predecessor starts

A start-to-start logical relationship describes a scenario where the successor activity cannot start until the predecessor activity starts. This means that there is a dependency between the two activities, and the successor activity must wait for the predecessor activity to begin before it can start. This relationship ensures that the timing and sequence of the activities are aligned properly in the project schedule. In contrast: - Option A (The successor's finish is dependent on the predecessor's start) describes a finish-to-start relationship. - Option B (The successor and predecessor start at the same time) describes a concurrent start relationship, not a start-to-start relationship. - Option D (The successor's start is independent of the predecessor's start) indicates a finish-to-finish relationship rather than a start-to-start relationship. Therefore, the correct description of a start-to-start logical relationship is that the successor cannot start until the predecessor starts, making option C the most appropriate answer.