What characterizes a technique in the context of project management?

  1. A set of guidelines for stakeholder engagement

  2. A systematic series of steps to achieve a result

  3. A high-level approach to strategic planning

  4. A blueprint for the project's architecture

The correct answer is: A systematic series of steps to achieve a result

A is incorrect because a technique is not limited to stakeholder engagement, it can also encompass other aspects of project management such as scheduling and budgeting. C is incorrect because a technique is not focused on strategic planning, but rather on practical steps that can be taken to achieve a specific result. D is incorrect because a technique is not a static blueprint, but rather a dynamic and adaptable series of steps to achieve a result.