What best describes a schedule activity?

  1. A task larger than a project phase

  2. An element of work performed during the course of a project

  3. A high-level overview of all project tasks

  4. A tool used for estimating project duration

The correct answer is: An element of work performed during the course of a project

A schedule activity is an element of work that is performed during the course of a project. It is a specific task or action that needs to be completed in order to move a project forward and achieve its objectives. Option A is incorrect because a project phase can include multiple tasks and activities. Option C is incorrect because a high-level overview does not necessarily include specific tasks and actions. Option D is incorrect because a schedule activity is not a tool used for estimating project duration, but rather a specific action that contributes to the overall project duration.