What are types of info management systems mentioned?

  1. Project communications, Project management plan updates

  2. Sender-receiver models, Choice of media

  3. Hard copy document management, Electronic communications management, Electronic project management tools

  4. Collecting/distributing performance info

The correct answer is: Hard copy document management, Electronic communications management, Electronic project management tools

The correct answer is C. Hard copy document management, electronic communications management, and electronic project management tools are types of information management systems mentioned in project management. Option A (Project communications, Project management plan updates) is not a type of information management system but rather related to project communication and updates to the project management plan. Option B (Sender-receiver models, Choice of media) is also not types of information management systems but refers more to communication models and methods rather than information management specifically. Option D (Collecting/distributing performance info) is related to performance management rather than information management systems.