What are the inputs of the perform integrated change control process?

  1. Change requests and project charter

  2. Project management plan and enterprise environmental factors

  3. Budget forecasts and control accounts

  4. Risk register and quality metrics

The correct answer is: Project management plan and enterprise environmental factors

The inputs of the perform integrated change control process include the project management plan and enterprise environmental factors. In this process, the project management plan is a crucial input as it contains all the detailed information on how the project will be executed, monitored, and controlled. It includes various subsidiary plans such as the scope management plan, schedule management plan, cost management plan, etc. Enterprise environmental factors are also important inputs as they refer to external environmental factors and internal organizational factors that can influence the project, such as market conditions, organizational culture, or government standards and regulations. While change requests are an outcome of the perform integrated change control process rather than inputs, the project charter is typically an input to the develop project management plan process, not the perform integrated change control process. Budget forecasts and control accounts are more relevant to cost management processes rather than integrated change control, and the risk register and quality metrics are more closely associated with risk management and quality management processes, respectively.