CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What are inputs to control procurements?

  1. Weather reports and travel schedules

  2. Project management plan, procurement documents, agreements, approved change requests, work reports, and data

  3. Stakeholder preferences and tastes

  4. Global economic reports

The correct answer is: Project management plan, procurement documents, agreements, approved change requests, work reports, and data

Inputs to control procurements include the project management plan, procurement documents, agreements, approved change requests, work reports, and data. These inputs are essential for effectively managing and controlling the procurement process throughout the project lifecycle. Weather reports and travel schedules, stakeholder preferences and tastes, and global economic reports are not direct inputs to control procurements and are not typically used for this purpose in project management.