What are inputs of the acquire project team process?

  1. Only HR management plan

  2. HR management plan, enterprise environmental factors, organizational process assets

  3. Project schedule and budget reports

  4. Market analysis reports

The correct answer is: HR management plan, enterprise environmental factors, organizational process assets

The correct answer is B. In the acquire project team process, the inputs include the HR management plan, enterprise environmental factors, and organizational process assets. The HR management plan is essential as it provides details on how the project team will be staffed, managed, and eventually released. Enterprise environmental factors can impact the way the team is acquired, such as the organizational culture or market conditions. Organizational process assets are also crucial inputs as they provide historical information, templates, and guidelines that can influence how the project team is acquired and managed. Options A, C, and D are incorrect as they do not align with the inputs typically associated with the acquire project team process.