What are considered project documents updates from control schedule?

  1. Schedule data, project schedule, risk register

  2. Project management plan, project charter

  3. Schedule control tools, monitoring and reporting methods

  4. Historical info and lessons learned, financial databases

The correct answer is: Schedule data, project schedule, risk register

Project documents updates from control schedule typically include schedule data, project schedule, and risk register. Schedule data and project schedule will be updated as changes are made to the project schedule during the control schedule process. The risk register may also be updated to reflect any changes in project risks that impact the schedule. Therefore, option A is the correct answer in this case. Options B, C, and D are not considered project documents updates from control schedule. Project management plan and project charter mentioned in option B are important project documents but are not specifically updated as part of control schedule. Schedule control tools, monitoring, and reporting methods in option C are used during control schedule to monitor and control the project schedule performance, but they are not updates themselves. Historical information and lessons learned, financial databases in option D are also not direct updates from control schedule.