How many processes are there in Project Scope Management?

  1. 4

  2. 5

  3. 6

  4. 7

The correct answer is: 6

Project Scope Management consists of 6 processes. These processes include: 1. Plan Scope Management 2. Collect Requirements 3. Define Scope 4. Create Work Breakdown Structure (WBS) 5. Validate Scope 6. Control Scope These processes are essential in managing the scope of a project effectively, ensuring that the project deliverables are defined, monitored, and controlled throughout the project lifecycle.