CAPM (Certified Associate in Project Management) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CAPM (Certified Associate in Project Management) exam with our informative quiz. Test your knowledge through multiple-choice questions and detailed explanations to boost your confidence and readiness for the certification.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


At what level should work and resources be assigned?

  1. The work package level

  2. The project level

  3. The task level

  4. The milestone level

The correct answer is: The work package level

Work and resources should be assigned at the work package level because it allows for more specific and focused management and monitoring of tasks. Assigning work and resources at the project level may be too broad and lack the necessary level of detail, while assigning at the task level can unnecessarily micro-manage and fragment tasks. Assigning at the milestone level does not provide enough structure and may overlook important details and tasks. Work package level is the most appropriate and efficient level for assigning work and resources.